A tremendous amount has been accomplished around the club in February. The Flourtown Kitchen is wrapping up on time. Below are some of the major project that have taken place.
Flourtown kitchen planning meeting in October 2019
Reviewing design work in November of 2019
Preconstruction Meeting
Demolition begins
Rough-in meeting prior to electrical and plumbing adjustments
Hood installation begins
Epoxy floor installation
Floor complete
New ceiling grid and LED light installation
Gas hook ups positioned for new equipment
New three-shelve unit installed with ten heaters
Equipment connection process
Time Lapse Video of the kitchen construction
Walk-in refrigerator and freezer installation
Walk-in refrigerator and freezer complete
Installation of character-grade, white oak floor
Sanding prior to staining
Finished floor installation
Electrical modifications prior to adding more fans on the patio
Unloading delivery of large trees
New trees prior to planting
Tree installation to the right of #3 Militia Hill Complete
Informational plaque placed near #4 Militia Hill tee explaining the history of the stone ruins
Expanded drop area on #17 Militia Hill
An eight-court pickleball social being hosted in our indoor facility following the painting of blended lines
Additional seating capacity created near the baby pool